Wells
The Well Data form is used to create or modify well data and lift tables for the simulation input. This panel is also used to synchronize well data with the static model.
-
Edit well data. Opens the well data view to display or modify well data for the current simulation case. Wells can also be imported via the Import wells button.
Edit wells Opens the Wells view.
Import wells Opens an import dialog through which you can import an ECLIPSE™ Schedule (*.SCH) file.
-
Connect wells to model. Here, connections are established to the upstream well completion and well history tables for each well. An entry in the well data table is either added or updated for each well in the static model. A new row is added if no well of the same name as the static model is found in the Well table.
Well category Selects the well category from which to make connections.
Connect wells Creates connections to well completions and well history.
-
For each connected well, update the well completion table and the well constraint table from the upstream workflow.
View wellbores Opens the Wellbore view.
Update wells Updates connected wells from static model. Updates the well constraint table(s) histories for selected wells. The history is created from the values in the well constraint table.
-
Edit or import lift tables.
Edit tables Opens the Production Well Tables/Injection Well Tables view. Inspect data and edit if necessary.
Import tables Click Import tables to open the data selection import window.
-
Edit well groups. Create well groups and assign simulation group constraints. Assign selected wells to well groups.
Edit groups Opens the well groups view for the simulation case. You can assign groups constraints for the gas production, injection, economic limit, consumption rates and production sales. Create new groups in the Well Groups tab, and specify the child and parent group in the Group Trees tab. To assign wells to the well group(s), see the following steps:
- Make sure you have selected the correct simulation case (Simulate > ECLIPSE > Simulation Case)
- On the Wells (Simulate > ECLIPSE > Wells) form, click on the Edit groups button under the Edit well groups section. This opens the well groups view for the simulation case.
- Open the Well Groups tab and enter the name of the group(s) that you want to create. Open the adjacent Group Trees tab and specify if the group is parent or child entity. Select a date/time in the first column from the drop down list of date/time that are used for the simulation case. The well group, along with the group constraints, is activated on this date and time of the simulation.
- Click on the Edit wells button on the Wells (Simulate > ECLIPSE > Wells) form to open the Wells view. On the Well Specification tab, assign the well(s) to the well group by selecting the group in the third column from the drop down list of well groups that are previously created.
Editing transmissibility factor manually
If you want to overwrite the default transmissibility factor values, you must remove the link between the 'JewelSuite Source' well and the 'Simulation' well. Follow the steps to manually edit transmissibility factor:
- On the Wells tab, Delete the JewelSuite source well entry for the well which you want to edit. Optionally use context menu of the cell to Clear Cells.
- Open the Well Perforation tab. Select the well that you want to edit from the table on left side. The grid connections with the well are tabulated on right side.
- Edit the transmissibility factors for the grid blocks perforated by the selected well. Make sure to Save the solution before building the simulation deck.